There is progress on the floor. 


The floor was completed in week 20.  It looks very good.  The in-wall speakers were installed.  They have tried to install the cherry paneling, but there was a problem.  Downstairs the painter are working. The faucets for the master bath were back ordered because Jado has stopped and is restarting their production line.  We remove the Jado valve that was installed and replace it with another brand.

The floors were complete on Oct 5th

Dinning room with a new floor

Did I tell you about the new floor?

New floor going down the stairs

Painting means parts of the house are uninhabitable

Painting in the master bedroom

We made negative progress on the bathroom.

We are having to replace the fixtures, because Jado fell on their sword.

An attempt to install the cherry paneling failed

The grain on the paneling did not match

The paneling laying on the dinning room floor

They got this far before they had to quit. Note that the cabinet for the TV is installed

This is the stack of lighting and plumbing fixtures waiting to be installed

The junk pile is now on the deck instead of the driveway.

The compass rose in the foyer

The compass rose in the foyer