Very little has been done in the last 3 weeks
The ceiling paint job turned out badly. The drywall company and
the contractor are dragging their feet. It took 12 days to get an
estimate for the work to be done. Once we gave them the go-ahead
they are not responding.
|
|
Marble tile has been added to the fireplace
|
|
|
New marble and a bunch of samples
|
|
|
The rail is being raised to accommodate the hot tub
|
|
|
|
Niches on the stair case have the cherry panels installed
|
|
|
The lyptus floor is in boxes in the garage
|
|
|
The ceiling paint job is holding up the job
|
|
|