These links show an progression of the kitchen remodel that we
did beginning on May 5th, 2008.
- Before During and Current - This gives you an
ideal of how bad it got and what it is like now
- Day 1 - These are pictures after the first day of
the kitchen remodel - May 5, 2008:
- Week 2 - Electric and plumbing rough-ins are done
- May 9th:
- Week 3 - The dry wall is up - May 22nd
- Week 4 - Some cabinets are in - June 6th
-
Week 5 - All base cabinets are in - June 13th
- Week 7 - Upper cabinets are in - June 20th
- Week 10 - First 2 coats of painting are on - July 11th
- Week 11 - The countertops are in - July 19th
- Week 12 - Not quite ready for party - July 26th
- Week 15 - Final inspection is done! - August 14th
|
|